Schedule Insight
Original Contract
—
Not set
Approved Baseline
—
Uses contract
Forecast finish
2 Mar 2027
—
Schedule Confidence
100
Excellent
Plugin-weighted · separate from governance
Forecast trend
Unchanged
No prior snapshot
Recoverable / Residual
—
From Optimisation (EDP-005)
Risk concentration: No concentrated delay
- No epics forecast later than Original Contract (18 active).
- Reporting Quality 100.
Reporting quality 100/100 — data completeness only; does not feed delivery KPIs. Manage baselines
Planned Progress
9.9%
96 / 972 business days
Through 26 Jul 2026
Earned Progress
6.9%
255.8 / 3708 earned hours
Programme variance -3.0%
Effort Consumed
255.8 / 3708 hrs
Consumed (proxy) / Estimated
6.9%
Programme — earned-based proxy
Simplus Effort
97.4 / 2448 hrs
Consumed (proxy) / Estimated
4.0%
Consultancy only — earned-based proxy
Programme Forecast
2 Mar 2027
Planned: 2 Mar 2027
On time
Healthy
7
7 of 8 workstreams
At Risk
0
0 of 8 workstreams
Epic
Overall Status
Owner
Start
Plan Finish
Forecast
Variance
Q3 2026
Q4 2026
Today
At Risk
Joint
22 Jun 2026
4 Sep 2026
24 Sep 2026
14d late
Review and finalise business process
Completed
LA
22 Jun 2026
26 Jun 2026
—
—
Outside period: Review and finalise business process, 22 Jun 2026 to 26 Jun 2026
Source Policy
Completed
LA
25 Jun 2026
26 Jun 2026
—
—
Outside period: Source Policy, 25 Jun 2026 to 26 Jun 2026
Draft Epics
Completed
Simplus
29 Jun 2026
1 Jul 2026
—
—
Epic Walk-Through
Completed
Simplus
2 Jul 2026
3 Jul 2026
—
—
Review + Validate Epics
In Progress
LA
6 Jul 2026
8 Jul 2026
—
—
Additional Business Inputs
In Progress
LA
6 Jul 2026
7 Jul 2026
—
—
Epic Finalisation
In Progress
LA
7 Jul 2026
8 Jul 2026
—
—
Epic Solutioning (Wireframe or Demo)
Pending
Simplus
9 Jul 2026
14 Jul 2026
—
—
Epic Playback
Pending
Simplus
15 Jul 2026
15 Jul 2026
—
—
Provide Feedback
Pending
LA
16 Jul 2026
16 Jul 2026
—
—
Epic Sign-Off
Milestone
Pending
LA
17 Jul 2026
17 Jul 2026
—
—
Create User Stories
Pending
Simplus
17 Jul 2026
21 Jul 2026
—
—
User Story Review
Pending
LA
22 Jul 2026
4 Aug 2026
—
—
Sign Off User Stories
Milestone
Pending
LA
5 Aug 2026
6 Aug 2026
—
—
Build
To Do
Simplus
7 Aug 2026
3 Sep 2026
—
—
Unit Testing
To Do
Simplus
4 Sep 2026
4 Sep 2026
—
—
Review and finalise business process
Completed
LA
22 Jun 2026
26 Jun 2026
—
—
Outside period: Review and finalise business process, 22 Jun 2026 to 26 Jun 2026
Source Policy
Completed
LA
25 Jun 2026
26 Jun 2026
—
—
Outside period: Source Policy, 25 Jun 2026 to 26 Jun 2026
Draft Epics
Completed
Simplus
29 Jun 2026
1 Jul 2026
—
—
Epic Walk-Through
Completed
Simplus
2 Jul 2026
3 Jul 2026
—
—
Review + Validate Epics
Completed
LA
6 Jul 2026
8 Jul 2026
—
—
Additional Business Inputs
Completed
LA
6 Jul 2026
7 Jul 2026
—
—
Epic Finalisation
Completed
LA
7 Jul 2026
8 Jul 2026
—
—
Epic Solutioning (Wireframe or Demo)
In Progress
Simplus
9 Jul 2026
14 Jul 2026
—
—
Epic Playback
Pending
Simplus
15 Jul 2026
15 Jul 2026
—
—
Provide Feedback
Pending
LA
16 Jul 2026
16 Jul 2026
—
—
Epic Sign-Off
Milestone
Pending
LA
17 Jul 2026
17 Jul 2026
—
—
Create User Stories
Pending
Simplus
17 Jul 2026
21 Jul 2026
—
—
User Story Review
Pending
LA
22 Jul 2026
4 Aug 2026
—
—
Sign Off User Stories
Milestone
Pending
LA
5 Aug 2026
6 Aug 2026
—
—
Build
To Do
Simplus
7 Aug 2026
3 Sep 2026
—
—
Unit Testing
To Do
Simplus
4 Sep 2026
4 Sep 2026
—
—
At Risk
Joint
22 Jun 2026
4 Sep 2026
6 Oct 2026
21d late
Review and finalise business process
Completed
LA
22 Jun 2026
26 Jun 2026
—
—
Outside period: Review and finalise business process, 22 Jun 2026 to 26 Jun 2026
Source Policy
Overdue
LA
25 Jun 2026
26 Jun 2026
—
—
Outside period: Source Policy, 25 Jun 2026 to 26 Jun 2026
Draft Epics
In Progress
Simplus
29 Jun 2026
1 Jul 2026
—
—
Epic Walk-Through
Pending
Simplus
2 Jul 2026
3 Jul 2026
—
—
Review + Validate Epics
Pending
LA
6 Jul 2026
8 Jul 2026
—
—
Additional Business Inputs
Pending
LA
6 Jul 2026
7 Jul 2026
—
—
Epic Finalisation
Pending
LA
7 Jul 2026
8 Jul 2026
—
—
Epic Solutioning (Wireframe or Demo)
Pending
Simplus
9 Jul 2026
14 Jul 2026
—
—
Epic Playback
Pending
Simplus
15 Jul 2026
15 Jul 2026
—
—
Provide Feedback
Pending
LA
16 Jul 2026
16 Jul 2026
—
—
Epic Sign-Off
Milestone
Pending
LA
17 Jul 2026
17 Jul 2026
—
—
Create User Stories
Pending
Simplus
17 Jul 2026
21 Jul 2026
—
—
User Story Review
Pending
LA
22 Jul 2026
4 Aug 2026
—
—
Sign Off User Stories
Milestone
Pending
LA
5 Aug 2026
6 Aug 2026
—
—
Build
To Do
Simplus
7 Aug 2026
3 Sep 2026
—
—
Unit Testing
To Do
Simplus
4 Sep 2026
4 Sep 2026
—
—
At Risk
Joint
22 Jun 2026
4 Sep 2026
11 Sep 2026
5d late
Review and finalise business process
Completed
LA
22 Jun 2026
26 Jun 2026
—
—
Outside period: Review and finalise business process, 22 Jun 2026 to 26 Jun 2026
Source Policy
Completed
LA
25 Jun 2026
26 Jun 2026
—
—
Outside period: Source Policy, 25 Jun 2026 to 26 Jun 2026
Draft Epics
Completed
Simplus
29 Jun 2026
1 Jul 2026
—
—
Epic Walk-Through
Completed
Simplus
2 Jul 2026
3 Jul 2026
—
—
Review + Validate Epics
Completed
LA
6 Jul 2026
8 Jul 2026
—
—
Additional Business Inputs
Completed
LA
6 Jul 2026
7 Jul 2026
—
—
Epic Finalisation
Completed
LA
7 Jul 2026
8 Jul 2026
—
—
Epic Solutioning (Wireframe or Demo)
Completed
Simplus
9 Jul 2026
14 Jul 2026
—
—
Epic Playback
Completed
Simplus
15 Jul 2026
15 Jul 2026
—
—
Provide Feedback
Completed
LA
16 Jul 2026
16 Jul 2026
—
—
Epic Sign-Off
Milestone
Completed
LA
17 Jul 2026
17 Jul 2026
—
—
Create User Stories
In Progress
Simplus
17 Jul 2026
21 Jul 2026
—
—
User Story Review
Pending
LA
22 Jul 2026
4 Aug 2026
—
—
Sign Off User Stories
Milestone
Pending
LA
5 Aug 2026
6 Aug 2026
—
—
Build
To Do
Simplus
7 Aug 2026
3 Sep 2026
—
—
Unit Testing
To Do
Simplus
4 Sep 2026
4 Sep 2026
—
—
Review and finalise business process
To Do
LA
7 Aug 2026
13 Aug 2026
—
—
Source Policy
To Do
LA
12 Aug 2026
13 Aug 2026
—
—
Draft Epics
To Do
Simplus
14 Aug 2026
18 Aug 2026
—
—
Epic Walk-Through
To Do
Simplus
19 Aug 2026
20 Aug 2026
—
—
Review + Validate Epics
To Do
LA
21 Aug 2026
25 Aug 2026
—
—
Additional Business Inputs
To Do
LA
21 Aug 2026
24 Aug 2026
—
—
Epic Finalisation
To Do
LA
24 Aug 2026
25 Aug 2026
—
—
Epic Solutioning (Wireframe or Demo)
To Do
Simplus
26 Aug 2026
31 Aug 2026
—
—
Epic Playback
To Do
Simplus
1 Sep 2026
1 Sep 2026
—
—
Provide Feedback
To Do
LA
2 Sep 2026
2 Sep 2026
—
—
Epic Sign-Off
Milestone
To Do
LA
3 Sep 2026
3 Sep 2026
—
—
Create User Stories
To Do
Simplus
3 Sep 2026
7 Sep 2026
—
—
User Story Review
To Do
LA
8 Sep 2026
21 Sep 2026
—
—
Sign Off User Stories
Milestone
To Do
LA
22 Sep 2026
23 Sep 2026
—
—
Build
To Do
Simplus
24 Sep 2026
22 Oct 2026
—
—
Unit Testing
To Do
Simplus
23 Oct 2026
23 Oct 2026
—
—
Review and finalise business process
To Do
LA
7 Aug 2026
13 Aug 2026
—
—
Source Policy
To Do
LA
12 Aug 2026
13 Aug 2026
—
—
Draft Epics
To Do
Simplus
14 Aug 2026
18 Aug 2026
—
—
Epic Walk-Through
To Do
Simplus
19 Aug 2026
20 Aug 2026
—
—
Review + Validate Epics
To Do
LA
21 Aug 2026
25 Aug 2026
—
—
Additional Business Inputs
To Do
LA
21 Aug 2026
24 Aug 2026
—
—
Epic Finalisation
To Do
LA
24 Aug 2026
25 Aug 2026
—
—
Epic Solutioning (Wireframe or Demo)
To Do
Simplus
26 Aug 2026
31 Aug 2026
—
—
Epic Playback
To Do
Simplus
1 Sep 2026
1 Sep 2026
—
—
Provide Feedback
To Do
LA
2 Sep 2026
2 Sep 2026
—
—
Epic Sign-Off
Milestone
To Do
LA
3 Sep 2026
3 Sep 2026
—
—
Create User Stories
To Do
Simplus
3 Sep 2026
7 Sep 2026
—
—
User Story Review
To Do
LA
8 Sep 2026
21 Sep 2026
—
—
Sign Off User Stories
Milestone
To Do
LA
22 Sep 2026
23 Sep 2026
—
—
Build
To Do
Simplus
24 Sep 2026
22 Oct 2026
—
—
Unit Testing
To Do
Simplus
23 Oct 2026
23 Oct 2026
—
—
To Do
Joint
7 Aug 2026
23 Oct 2026
23 Oct 2026
On Track
Review and finalise business process
To Do
LA
7 Aug 2026
13 Aug 2026
—
—
Source Policy
To Do
LA
12 Aug 2026
13 Aug 2026
—
—
Draft Epics
To Do
Simplus
14 Aug 2026
18 Aug 2026
—
—
Epic Walk-Through
To Do
Simplus
19 Aug 2026
20 Aug 2026
—
—
Review + Validate Epics
To Do
LA
21 Aug 2026
25 Aug 2026
—
—
Additional Business Inputs
To Do
LA
21 Aug 2026
24 Aug 2026
—
—
Epic Finalisation
To Do
LA
24 Aug 2026
25 Aug 2026
—
—
Epic Solutioning (Wireframe or Demo)
To Do
Simplus
26 Aug 2026
31 Aug 2026
—
—
Epic Playback
To Do
Simplus
1 Sep 2026
1 Sep 2026
—
—
Provide Feedback
To Do
LA
2 Sep 2026
2 Sep 2026
—
—
Epic Sign-Off
Milestone
To Do
LA
3 Sep 2026
3 Sep 2026
—
—
Create User Stories
To Do
Simplus
3 Sep 2026
7 Sep 2026
—
—
User Story Review
To Do
LA
8 Sep 2026
21 Sep 2026
—
—
Sign Off User Stories
Milestone
To Do
LA
22 Sep 2026
23 Sep 2026
—
—
Build
To Do
Simplus
24 Sep 2026
22 Oct 2026
—
—
Unit Testing
To Do
Simplus
23 Oct 2026
23 Oct 2026
—
—
To Do
Joint
7 Aug 2026
23 Oct 2026
23 Oct 2026
On Track
Review and finalise business process
To Do
LA
7 Aug 2026
13 Aug 2026
—
—
Source Policy
To Do
LA
12 Aug 2026
13 Aug 2026
—
—
Draft Epics
To Do
Simplus
14 Aug 2026
18 Aug 2026
—
—
Epic Walk-Through
To Do
Simplus
19 Aug 2026
20 Aug 2026
—
—
Review + Validate Epics
To Do
LA
21 Aug 2026
25 Aug 2026
—
—
Additional Business Inputs
To Do
LA
21 Aug 2026
24 Aug 2026
—
—
Epic Finalisation
To Do
LA
24 Aug 2026
25 Aug 2026
—
—
Epic Solutioning (Wireframe or Demo)
To Do
Simplus
26 Aug 2026
31 Aug 2026
—
—
Epic Playback
To Do
Simplus
1 Sep 2026
1 Sep 2026
—
—
Provide Feedback
To Do
LA
2 Sep 2026
2 Sep 2026
—
—
Epic Sign-Off
Milestone
To Do
LA
3 Sep 2026
3 Sep 2026
—
—
Create User Stories
To Do
Simplus
3 Sep 2026
7 Sep 2026
—
—
User Story Review
To Do
LA
8 Sep 2026
21 Sep 2026
—
—
Sign Off User Stories
Milestone
To Do
LA
22 Sep 2026
23 Sep 2026
—
—
Build
To Do
Simplus
24 Sep 2026
22 Oct 2026
—
—
Unit Testing
To Do
Simplus
23 Oct 2026
23 Oct 2026
—
—
To Do
Joint
24 Sep 2026
11 Dec 2026
11 Dec 2026
On Track
Review and finalise business process
To Do
LA
24 Sep 2026
1 Oct 2026
—
—
Source Policy
To Do
LA
30 Sep 2026
1 Oct 2026
—
—
Draft Epics
To Do
Simplus
2 Oct 2026
6 Oct 2026
—
—
Epic Walk-Through
To Do
Simplus
7 Oct 2026
8 Oct 2026
—
—
Review + Validate Epics
To Do
LA
9 Oct 2026
13 Oct 2026
—
—
Additional Business Inputs
To Do
LA
9 Oct 2026
12 Oct 2026
—
—
Epic Finalisation
To Do
LA
12 Oct 2026
13 Oct 2026
—
—
Epic Solutioning (Wireframe or Demo)
To Do
Simplus
14 Oct 2026
19 Oct 2026
—
—
Epic Playback
To Do
Simplus
20 Oct 2026
20 Oct 2026
—
—
Provide Feedback
To Do
LA
21 Oct 2026
21 Oct 2026
—
—
Epic Sign-Off
Milestone
To Do
LA
22 Oct 2026
22 Oct 2026
—
—
Create User Stories
To Do
Simplus
22 Oct 2026
26 Oct 2026
—
—
User Story Review
To Do
LA
27 Oct 2026
10 Nov 2026
—
—
Sign Off User Stories
Milestone
To Do
LA
11 Nov 2026
12 Nov 2026
—
—
Build
To Do
Simplus
13 Nov 2026
10 Dec 2026
—
—
Unit Testing
To Do
Simplus
11 Dec 2026
11 Dec 2026
—
—
To Do
Joint
24 Sep 2026
11 Dec 2026
11 Dec 2026
On Track
Review and finalise business process
To Do
LA
24 Sep 2026
1 Oct 2026
—
—
Source Policy
To Do
LA
30 Sep 2026
1 Oct 2026
—
—
Draft Epics
To Do
Simplus
2 Oct 2026
6 Oct 2026
—
—
Epic Walk-Through
To Do
Simplus
7 Oct 2026
8 Oct 2026
—
—
Review + Validate Epics
To Do
LA
9 Oct 2026
13 Oct 2026
—
—
Additional Business Inputs
To Do
LA
9 Oct 2026
12 Oct 2026
—
—
Epic Finalisation
To Do
LA
12 Oct 2026
13 Oct 2026
—
—
Epic Solutioning (Wireframe or Demo)
To Do
Simplus
14 Oct 2026
19 Oct 2026
—
—
Epic Playback
To Do
Simplus
20 Oct 2026
20 Oct 2026
—
—
Provide Feedback
To Do
LA
21 Oct 2026
21 Oct 2026
—
—
Epic Sign-Off
Milestone
To Do
LA
22 Oct 2026
22 Oct 2026
—
—
Create User Stories
To Do
Simplus
22 Oct 2026
26 Oct 2026
—
—
User Story Review
To Do
LA
27 Oct 2026
10 Nov 2026
—
—
Sign Off User Stories
Milestone
To Do
LA
11 Nov 2026
12 Nov 2026
—
—
Build
To Do
Simplus
13 Nov 2026
10 Dec 2026
—
—
Unit Testing
To Do
Simplus
11 Dec 2026
11 Dec 2026
—
—
To Do
Joint
24 Sep 2026
11 Dec 2026
11 Dec 2026
On Track
Review and finalise business process
To Do
LA
24 Sep 2026
1 Oct 2026
—
—
Source Policy
To Do
LA
30 Sep 2026
1 Oct 2026
—
—
Draft Epics
To Do
Simplus
2 Oct 2026
6 Oct 2026
—
—
Epic Walk-Through
To Do
Simplus
7 Oct 2026
8 Oct 2026
—
—
Review + Validate Epics
To Do
LA
9 Oct 2026
13 Oct 2026
—
—
Additional Business Inputs
To Do
LA
9 Oct 2026
12 Oct 2026
—
—
Epic Finalisation
To Do
LA
12 Oct 2026
13 Oct 2026
—
—
Epic Solutioning (Wireframe or Demo)
To Do
Simplus
14 Oct 2026
19 Oct 2026
—
—
Epic Playback
To Do
Simplus
20 Oct 2026
20 Oct 2026
—
—
Provide Feedback
To Do
LA
21 Oct 2026
21 Oct 2026
—
—
Epic Sign-Off
Milestone
To Do
LA
22 Oct 2026
22 Oct 2026
—
—
Create User Stories
To Do
Simplus
22 Oct 2026
26 Oct 2026
—
—
User Story Review
To Do
LA
27 Oct 2026
10 Nov 2026
—
—
Sign Off User Stories
Milestone
To Do
LA
11 Nov 2026
12 Nov 2026
—
—
Build
To Do
Simplus
13 Nov 2026
10 Dec 2026
—
—
Unit Testing
To Do
Simplus
11 Dec 2026
11 Dec 2026
—
—
To Do
Joint
24 Sep 2026
11 Dec 2026
11 Dec 2026
On Track
Review and finalise business process
To Do
LA
24 Sep 2026
1 Oct 2026
—
—
Source Policy
To Do
LA
30 Sep 2026
1 Oct 2026
—
—
Draft Epics
To Do
Simplus
2 Oct 2026
6 Oct 2026
—
—
Epic Walk-Through
To Do
Simplus
7 Oct 2026
8 Oct 2026
—
—
Review + Validate Epics
To Do
LA
9 Oct 2026
13 Oct 2026
—
—
Additional Business Inputs
To Do
LA
9 Oct 2026
12 Oct 2026
—
—
Epic Finalisation
To Do
LA
12 Oct 2026
13 Oct 2026
—
—
Epic Solutioning (Wireframe or Demo)
To Do
Simplus
14 Oct 2026
19 Oct 2026
—
—
Epic Playback
To Do
Simplus
20 Oct 2026
20 Oct 2026
—
—
Provide Feedback
To Do
LA
21 Oct 2026
21 Oct 2026
—
—
Epic Sign-Off
Milestone
To Do
LA
22 Oct 2026
22 Oct 2026
—
—
Create User Stories
To Do
Simplus
22 Oct 2026
26 Oct 2026
—
—
User Story Review
To Do
LA
27 Oct 2026
10 Nov 2026
—
—
Sign Off User Stories
Milestone
To Do
LA
11 Nov 2026
12 Nov 2026
—
—
Build
To Do
Simplus
13 Nov 2026
10 Dec 2026
—
—
Unit Testing
To Do
Simplus
11 Dec 2026
11 Dec 2026
—
—
To Do
Joint
6 Nov 2026
27 Jan 2027
27 Jan 2027
On Track
Review and finalise business process
To Do
LA
6 Nov 2026
12 Nov 2026
—
—
Source Policy
To Do
LA
11 Nov 2026
12 Nov 2026
—
—
Draft Epics
To Do
Simplus
13 Nov 2026
17 Nov 2026
—
—
Epic Walk-Through
To Do
Simplus
18 Nov 2026
19 Nov 2026
—
—
Review + Validate Epics
To Do
LA
20 Nov 2026
24 Nov 2026
—
—
Additional Business Inputs
To Do
LA
20 Nov 2026
23 Nov 2026
—
—
Epic Finalisation
To Do
LA
23 Nov 2026
24 Nov 2026
—
—
Epic Solutioning (Wireframe or Demo)
To Do
Simplus
25 Nov 2026
30 Nov 2026
—
—
Epic Playback
To Do
Simplus
1 Dec 2026
1 Dec 2026
—
—
Provide Feedback
To Do
LA
2 Dec 2026
2 Dec 2026
—
—
Epic Sign-Off
Milestone
To Do
LA
3 Dec 2026
3 Dec 2026
—
—
Create User Stories
To Do
Simplus
3 Dec 2026
7 Dec 2026
—
—
User Story Review
To Do
LA
8 Dec 2026
21 Dec 2026
—
—
Sign Off User Stories
Milestone
To Do
LA
22 Dec 2026
23 Dec 2026
—
—
Build
To Do
Simplus
24 Dec 2026
25 Jan 2027
—
—
Unit Testing
To Do
Simplus
27 Jan 2027
27 Jan 2027
—
—
Outside period: Unit Testing, 27 Jan 2027 to 27 Jan 2027
Review and finalise business process
To Do
LA
6 Nov 2026
12 Nov 2026
—
—
Source Policy
To Do
LA
11 Nov 2026
12 Nov 2026
—
—
Draft Epics
To Do
Simplus
13 Nov 2026
17 Nov 2026
—
—
Epic Walk-Through
To Do
Simplus
18 Nov 2026
19 Nov 2026
—
—
Review + Validate Epics
To Do
LA
20 Nov 2026
24 Nov 2026
—
—
Additional Business Inputs
To Do
LA
20 Nov 2026
23 Nov 2026
—
—
Epic Finalisation
To Do
LA
23 Nov 2026
24 Nov 2026
—
—
Epic Solutioning (Wireframe or Demo)
To Do
Simplus
25 Nov 2026
30 Nov 2026
—
—
Epic Playback
To Do
Simplus
1 Dec 2026
1 Dec 2026
—
—
Provide Feedback
To Do
LA
2 Dec 2026
2 Dec 2026
—
—
Epic Sign-Off
Milestone
To Do
LA
3 Dec 2026
3 Dec 2026
—
—
Create User Stories
To Do
Simplus
3 Dec 2026
7 Dec 2026
—
—
User Story Review
To Do
LA
8 Dec 2026
21 Dec 2026
—
—
Sign Off User Stories
Milestone
To Do
LA
22 Dec 2026
23 Dec 2026
—
—
Build
To Do
Simplus
24 Dec 2026
25 Jan 2027
—
—
Unit Testing
To Do
Simplus
27 Jan 2027
27 Jan 2027
—
—
Outside period: Unit Testing, 27 Jan 2027 to 27 Jan 2027
Review and finalise business process
To Do
LA
6 Nov 2026
12 Nov 2026
—
—
Source Policy
To Do
LA
11 Nov 2026
12 Nov 2026
—
—
Draft Epics
To Do
Simplus
13 Nov 2026
17 Nov 2026
—
—
Epic Walk-Through
To Do
Simplus
18 Nov 2026
19 Nov 2026
—
—
Review + Validate Epics
To Do
LA
20 Nov 2026
24 Nov 2026
—
—
Additional Business Inputs
To Do
LA
20 Nov 2026
23 Nov 2026
—
—
Epic Finalisation
To Do
LA
23 Nov 2026
24 Nov 2026
—
—
Epic Solutioning (Wireframe or Demo)
To Do
Simplus
25 Nov 2026
30 Nov 2026
—
—
Epic Playback
To Do
Simplus
1 Dec 2026
1 Dec 2026
—
—
Provide Feedback
To Do
LA
2 Dec 2026
2 Dec 2026
—
—
Epic Sign-Off
Milestone
To Do
LA
3 Dec 2026
3 Dec 2026
—
—
Create User Stories
To Do
Simplus
3 Dec 2026
7 Dec 2026
—
—
User Story Review
To Do
LA
8 Dec 2026
21 Dec 2026
—
—
Sign Off User Stories
Milestone
To Do
LA
22 Dec 2026
23 Dec 2026
—
—
Build
To Do
Simplus
24 Dec 2026
25 Jan 2027
—
—
Unit Testing
To Do
Simplus
27 Jan 2027
27 Jan 2027
—
—
Outside period: Unit Testing, 27 Jan 2027 to 27 Jan 2027
Review and finalise business process
To Do
LA
6 Nov 2026
12 Nov 2026
—
—
Source Policy
To Do
LA
11 Nov 2026
12 Nov 2026
—
—
Draft Epics
To Do
Simplus
13 Nov 2026
17 Nov 2026
—
—
Epic Walk-Through
To Do
Simplus
18 Nov 2026
19 Nov 2026
—
—
Review + Validate Epics
To Do
LA
20 Nov 2026
24 Nov 2026
—
—
Additional Business Inputs
To Do
LA
20 Nov 2026
23 Nov 2026
—
—
Epic Finalisation
To Do
LA
23 Nov 2026
24 Nov 2026
—
—
Epic Solutioning (Wireframe or Demo)
To Do
Simplus
25 Nov 2026
30 Nov 2026
—
—
Epic Playback
To Do
Simplus
1 Dec 2026
1 Dec 2026
—
—
Provide Feedback
To Do
LA
2 Dec 2026
2 Dec 2026
—
—
Epic Sign-Off
Milestone
To Do
LA
3 Dec 2026
3 Dec 2026
—
—
Create User Stories
To Do
Simplus
3 Dec 2026
7 Dec 2026
—
—
User Story Review
To Do
LA
8 Dec 2026
21 Dec 2026
—
—
Sign Off User Stories
Milestone
To Do
LA
22 Dec 2026
23 Dec 2026
—
—
Build
To Do
Simplus
24 Dec 2026
25 Jan 2027
—
—
Unit Testing
To Do
Simplus
27 Jan 2027
27 Jan 2027
—
—
Outside period: Unit Testing, 27 Jan 2027 to 27 Jan 2027
To Do
Joint
10 Dec 2026
2 Mar 2027
2 Mar 2027
On Track
Review and finalise business process
To Do
LA
10 Dec 2026
16 Dec 2026
—
—
Source Policy
To Do
LA
15 Dec 2026
16 Dec 2026
—
—
Draft Epics
To Do
Simplus
17 Dec 2026
21 Dec 2026
—
—
Epic Walk-Through
To Do
Simplus
22 Dec 2026
23 Dec 2026
—
—
Review + Validate Epics
To Do
LA
24 Dec 2026
30 Dec 2026
—
—
Additional Business Inputs
To Do
LA
24 Dec 2026
29 Dec 2026
—
—
Epic Finalisation
To Do
LA
29 Dec 2026
30 Dec 2026
—
—
Epic Solutioning (Wireframe or Demo)
To Do
Simplus
31 Dec 2026
6 Jan 2027
—
—
Epic Playback
To Do
Simplus
7 Jan 2027
7 Jan 2027
—
—
Outside period: Epic Playback, 7 Jan 2027 to 7 Jan 2027
Provide Feedback
To Do
LA
8 Jan 2027
8 Jan 2027
—
—
Outside period: Provide Feedback, 8 Jan 2027 to 8 Jan 2027
Epic Sign-Off
Milestone
To Do
LA
11 Jan 2027
11 Jan 2027
—
—
Outside period: Epic Sign-Off, 11 Jan 2027 to 11 Jan 2027
Create User Stories
To Do
Simplus
11 Jan 2027
13 Jan 2027
—
—
Outside period: Create User Stories, 11 Jan 2027 to 13 Jan 2027
User Story Review
To Do
LA
14 Jan 2027
28 Jan 2027
—
—
Outside period: User Story Review, 14 Jan 2027 to 28 Jan 2027
Sign Off User Stories
Milestone
To Do
LA
29 Jan 2027
1 Feb 2027
—
—
Outside period: Sign Off User Stories, 29 Jan 2027 to 1 Feb 2027
Build
To Do
Simplus
2 Feb 2027
1 Mar 2027
—
—
Outside period: Build, 2 Feb 2027 to 1 Mar 2027
Unit Testing
To Do
Simplus
2 Mar 2027
2 Mar 2027
—
—
Outside period: Unit Testing, 2 Mar 2027 to 2 Mar 2027
Review and finalise business process
To Do
LA
10 Dec 2026
16 Dec 2026
—
—
Source Policy
To Do
LA
15 Dec 2026
16 Dec 2026
—
—
Draft Epics
To Do
Simplus
17 Dec 2026
21 Dec 2026
—
—
Epic Walk-Through
To Do
Simplus
22 Dec 2026
23 Dec 2026
—
—
Review + Validate Epics
To Do
LA
24 Dec 2026
30 Dec 2026
—
—
Additional Business Inputs
To Do
LA
24 Dec 2026
29 Dec 2026
—
—
Epic Finalisation
To Do
LA
29 Dec 2026
30 Dec 2026
—
—
Epic Solutioning (Wireframe or Demo)
To Do
Simplus
31 Dec 2026
6 Jan 2027
—
—
Epic Playback
To Do
Simplus
7 Jan 2027
7 Jan 2027
—
—
Outside period: Epic Playback, 7 Jan 2027 to 7 Jan 2027
Provide Feedback
To Do
LA
8 Jan 2027
8 Jan 2027
—
—
Outside period: Provide Feedback, 8 Jan 2027 to 8 Jan 2027
Epic Sign-Off
Milestone
To Do
LA
11 Jan 2027
11 Jan 2027
—
—
Outside period: Epic Sign-Off, 11 Jan 2027 to 11 Jan 2027
Create User Stories
To Do
Simplus
11 Jan 2027
13 Jan 2027
—
—
Outside period: Create User Stories, 11 Jan 2027 to 13 Jan 2027
User Story Review
To Do
LA
14 Jan 2027
28 Jan 2027
—
—
Outside period: User Story Review, 14 Jan 2027 to 28 Jan 2027
Sign Off User Stories
Milestone
To Do
LA
29 Jan 2027
1 Feb 2027
—
—
Outside period: Sign Off User Stories, 29 Jan 2027 to 1 Feb 2027
Build
To Do
Simplus
2 Feb 2027
1 Mar 2027
—
—
Outside period: Build, 2 Feb 2027 to 1 Mar 2027
Unit Testing
To Do
Simplus
2 Mar 2027
2 Mar 2027
—
—
Outside period: Unit Testing, 2 Mar 2027 to 2 Mar 2027
Scroll the timeline left/right for the full period · scroll down for more epics · expand rows for activities
Build Readiness Funnel
Checkpoint counts = epics that completed that step. Build Ready = fully done epics
Business Review
Epic Definition
Solution Design
Epic Progress by Stage
Business Review9%
Epic Definition8%
Solution Design5%
Business Playback5%
Story Elaboration0%
Build0%
Upcoming Milestones (Next 30 Days)
- 6 Aug — Sign Off User Stories (GL-03: Charge Agreement, Outcome Manage…)
- 6 Aug — Sign Off User Stories (FN-01B: Claims Adjustment)
- 6 Aug — Sign Off User Stories (GL-04: Transfer Request, Court Details …)
- 6 Aug — Sign Off User Stories (FN-03: Section 46 Final Contribution, D…)
Executive Attention
Top overdue schedule risks — up to 2 overdue items per epic.
| Epic | Task | Reason | Due | Overdue | Owner | Assignee |
|---|---|---|---|---|---|---|
|
GL-04: Transfer Request, Court Details & Justice Link Court Integration
DEL-3371
|
Source Policy | Overdue on critical path | 26 Jun 2026 | 30 days | LA | Loanne Allsopp |
|
GL-04: Transfer Request, Court Details & Justice Link Court Integration
DEL-3371
|
Draft Epics | Overdue on critical path | 1 Jul 2026 | 25 days | Simplus | Anjali Rakesh |
|
GL-03: Charge Agreement, Outcome Management
DEL-3370
|
Additional Business Inputs | Overdue | 7 Jul 2026 | 19 days | LA | Jessica Garden |
|
GL-03: Charge Agreement, Outcome Management
DEL-3370
|
Epic Finalisation | Overdue on critical path | 8 Jul 2026 | 18 days | LA | Jessica Garden |
|
FN-01B: Claims Adjustment
DEL-3372
|
Epic Solutioning (Wireframe or Demo) | Overdue on critical path | 14 Jul 2026 | 12 days | Simplus | Omkar Jante |
|
FN-01B: Claims Adjustment
DEL-3372
|
Epic Playback | Overdue on critical path | 15 Jul 2026 | 11 days | Simplus | Anjali Rakesh |
|
FN-03: Section 46 Final Contribution, Discretion Outcomes & Integration
DEL-3374
|
Create User Stories | Overdue on critical path | 21 Jul 2026 | 5 days | Simplus | Anjali Rakesh |
Current: Unknown — Create User Stories